Skip to main content

Royal Canadian Air Cadets · Level Two

M290.02 Construct a lean-to-style shelter

PO 290 – Participate in a field exercise

Source

Extracts of the official PDFs covering only this EO, stamped on every page with their source and cache date. They are convenience copies, not the publication of record.

  • Instructional Guide (IG) A-CR-CCP-802/PF-001 pp. 885–892 Full official IG ↗

    Copied 2026-11-08 from the official publication (issued 2016-09-13). The official publication is authoritative.

  • Qualification Standard and Plan (QSP) A-CR-CCP-802/PG-001 pp. 289–292 Full official QSP ↗

    Copied 2026-11-08 from the official publication (issued 2016-09-13). The official publication is authoritative.

Performance, conditions and standard

The three essential parts of the EO, from the QSP lesson specification. The standard is what the cadet must achieve; everything below it is how the QSP suggests getting there.

Periods
3 periods
Total time
90 min
Method
Interactive Lecture, Demonstration, Performance
Performance

Construct a Lean-to-style Shelter

Conditions
Given:
  • Groundsheets
  • Knife
  • Shovel
  • Pegs
  • Rope/twine
  • Natural materials
  • Supervision
  • Assistance as required

Environmental: Field setting during the day and large enough to accommodate the entire group and shelter construction.

Standard · The cadet shall meet this standard

In accordance with specified references and as a member of a group of no more than four, the cadet shall construct a lean-to-style shelter by:

a. gathering materials;

b. selecting a site; and

c. tying and lashing cross pieces and supports.

Lesson objective (IG)
By the end of this lesson the cadet shall be expected to have constructed a lean-to-style shelter.

Assessment

Not assessed: the QSP gives no test details for this EO (N/A).

All Level Two assessments →

Before the lesson

From the IG's preparation section. Tick them off the night before.

Pre-lesson instructions

No specific preparation beyond the standard reminders.

Standard reminders (every lesson)
  • Resources needed for the delivery of this lesson are listed in the lesson specification located in A-CR-CCP-802/ PG-001, Chapter 4. Specific uses for said resources are identified throughout the Instructional Guide within the TP for which they are required.
  • Review the lesson content and become familiar with the material prior to delivering the lesson.

Safety

  • Review safe handling of a knife to include:
  • always cut away from the body;
  • do not let others stand too close to you;
  • do not leave a knife unattended on the ground;
  • sheath a knife when not in use; and
  • never throw a knife for any reason.
  • “Shelters”, Wilderness Survival. Copyright 2007 Jalic Inc. Retrieved 9 March 2007, from http://www.wilderness-survival.net/shelters-s.php
  • Figure 1 Lean-to-style Shelter
  • Adequate supervision will ensure the cadets do not misuse the equipment.

Instructional strategy (lesson specification)

The lesson specification describes the instructional strategy to apply to this EO: supporting teaching points, references, learning activities, estimated timings and assessment directions. They support the standard above; they are not the standard.

Supporting teaching points
TP1 Interactive Lecture · 20 min

Explain the importance of site selection and assist cadets in selecting a site for their lean-to-style shelter. Review the following:

a. Site selection. Site selection should begin before dark if possible. The shelter should be built near a source of water, building materials (trees, boughs) and fuel.

b. Land considerations. The following points are to be kept in mind:

1. The area must be large enough for the planned shelter.

2. The area should not be at the bottom of a hill. It should be relatively flat, but slightly sloped to allow for drainage.

3. Dry river gullies, canyons and flood plains should be avoided.

c. Water considerations. The following points are to be kept in mind:

1. The shelter should be built away from the water in order to avoid insects.

2. The shelter should be built away from the source of drinking water.

d. Animal and insect considerations. The following points are to be kept in mind:

1. Avoid setting up a shelter where there are animal trails or water holes.

2. Fast flowing streams will have fewer insects nearby than still water.

3. Avoid areas infested with ants or bees.

e. Other considerations. The following points are to be kept in mind:

1. There should be an area nearby to construct signals.

2. The entrance of the shelter should face the sun to add warmth and to increase morale.

3. Very thick woods should be avoided as it will be hard to dry the shelter or fuel.

4. Try to find a natural windbreak or a place that is away from strong wind currents.

5. Avoid swampy terrain.

6. A place for a fire should be located in front of the opening of the shelter.

Ref: C3-002 (pp. 242–243), C3-003 (p. 101)

TP2 Demonstration · 20 min

Explain and demonstrate the procedure for constructing a lean-to-style shelter, to include:

a. obtaining the appropriate supplies, to include:

1. groundsheets;

2. knife;

3. shovel;

4. pegs;

5. rope/twine; and

6. natural materials; and

b. tying and lashing cross-pieces and vertical supports;

c. checking each groundsheet for fatigue and holes;

d. tying each end of the groundsheet to cross-pieces and supports, ensuring they are to waist height of the tallest person;

e. ensuring the groundsheet is pulled tight between the cross-pieces and supports;

f. pulling the bottom of the groundsheet out and pegging each grommet to the ground; and

g. digging small trenches around the shelter to allow for effective drainage.

Ref: C3-002 (p. 250), C3-003 (p. 101), C3-118

TP3 Performance · 40 min

Have the cadets, in groups of no more than four, construct a lean-to-style shelter, taking into account the site selection considerations.

Ref: A0-039

Time
  • Introduction / Conclusion10 min
  • Interactive Lecture20 min
  • Demonstration20 min
  • Performance40 min
  • Total90 min
Substantiation

a. An interactive lecture was chosen for TP1 to present basic material and give direction on procedures.

b. Demonstration was chosen for TP2 as it allows the instructor to explain and demonstrate the skill the cadet is expected to acquire.

c. Performance was chosen for TP3 as it provides an opportunity for the cadets to practice building a lean-to-style shelter under supervision.

Training aids
  • Groundsheets
  • Example of a good shelter site
  • Example of a poor shelter site
  • Completed lean-to-style shelter for illustration purposes
  • Knife
  • Shovel
  • Pegs
  • Rope/twine
Learning aids
  • Groundsheets
  • Lengths of rope/twine
  • Shovel
  • Items found in a natural setting
  • Tree branches
  • Pegs
Remarks

a. If lean-to-style shelters cannot be constructed, another style shelter (e.g. a bivouac tent, or a tarpaulin between trees) may be substituted.

b. The directives found in CATO 11-08, Environmental Protection and Stewardship, are to be followed during this lesson.

References
  • A0-039 D Cdts 3. (1997). CATO 11-08. Environmental Protection and Stewardship. In CATO Vol. 1 General (pp.1–11). Ottawa, ON: Department of National Defence.
  • C3-002 (ISBN 0-00-653140-7) Wiseman, J. (1999). The SAS Survival Handbook. Hammersmith, London: HarperCollins Publishers.
  • C3-003 (ISBN 1-896713-00-9) Tawrell, P. (1996). Camping and Wilderness Survival: The Ultimate Outdoors Book. Green Valley, ON: Falcon Distribution.
  • C3-118 Wilderness Survival. (2007). Shelters. Retrieved 9 March 2007, from http://www.wilderness-survival.net/shelters-2.php.

After the lesson

Instructor notes / remarks

  • If lean-to-style shelters cannot be constructed, another style shelter (e.g. a bivouac tent, or a tarpaulin between trees) may be substituted.
  • The directives found in CATO 11-08, Environmental Protection and Stewardship , are to be followed during this lesson.

Instructional guide — a starting point for your lesson

In the IG's own words, it "provides instructors with the base means from which to deliver training" and "instructors are also encouraged to modify and / or enhance the activities, as long as they continue to contribute to enabling objective achievement." Build your lesson from it; teach to the standard above.

Show the full text

Plain-text extraction of the IG section for this EO. Images, tables and layout are only in the PDF.

PROFICIENCY LEVEL TWO

EO M290.02 – CONSTRUCT A LEAN-TO-STYLE SHELTER

Total Time: 90 min

PREPARATION

PRE-LESSON INSTRUCTIONS

Resources needed for the delivery of this lesson are listed in the lesson specification located in A-CR-CCP-802/ PG-001, Chapter 4. Specific uses for said resources are identified throughout the Instructional Guide within the TP for which they are required.

Review the lesson content and become familiar with the material prior to delivering the lesson.

PRE-LESSON ASSIGNMENT

N/A.

APPROACH

An interactive lecture was chosen for TP1 to present basic material and give direction on procedures for constructing a lean-to-style shelter.

Demonstration was chosen for TP2 as it allows the instructor to explain and demonstrate the skill the cadet is expected to acquire.

Performance was chosen for TP3 as it provides an opportunity for the cadets to practice building a lean-to-style shelter under supervision.

INTRODUCTION

REVIEW

N/A.

OBJECTIVES

By the end of this lesson the cadet shall be expected to have constructed a lean-to-style shelter.

IMPORTANCE

It is important for cadets to know how to construct a lean-to-style shelter as it can protect them from weather, animals and insects in a survival situation. Shelters can also provide warmth, shade and comfort.

Teaching point 1 Explain the Importance of Site Selection

Time: 20 min Method: Interactive Lecture

SELECTING A SITE FOR CONSTRUCTION OF A LEAN-TO-STYLE SHELTER

• The site selection should begin before darkness, if possible.

• The shelter should be built near materials to build the shelter (trees, boughs) and fuel for the fire.

Ensure cadets understand that although trees may offer protection, those with dead branches or on windswept fields may be dangerous. Check above and around the lean-to site for dead and standing trees or branches.

Land Considerations

• The area selected must be large enough to accommodate the planned shelter.

• The area selected should not be at the bottom of a hill.

• The area should be relatively flat with only a slight slope to allow for drainage.

• Dry river gullies, canyons and flood plains should be avoided. Water Considerations

• The shelter should be built away from still water in order to avoid insects.

• The shelter should be built away from the source of drinking water. Animal and Insect Considerations

• Avoid setting up a shelter where there are animal trails or water holes.

• Fast flowing streams will have fewer insects nearby than still water.

• Avoid areas infested with ants or bees. Other Considerations

• There should be an area nearby to construct signals.

• The entrance of the shelter should face the sun to add warmth and increase morale.

• Very thick woods should be avoided as it will be hard to dry the shelter or fuel.

• Try to find a natural windbreak or a place that is away from strong wind currents.

• Avoid swampy terrain.

• A place for a fire should be located in front of the opening of the shelter.

• Be aware of the prevailing winds.

CONFIRMATION OF TEACHING POINT 1

QUESTIONS

Q1. Name three land considerations when building a shelter.

Q2. Name three animal considerations when building a shelter.

Q3. Name three other considerations when building a shelter.

ANTICIPATED ANSWERS

A1. The area must be large enough for the planned shelter; the area should not be at the bottom of a hill; and it should be relatively flat with only a slight slope to allow for drainage.

A2. Avoid building shelters near animal trails or water holes; fast flowing streams will have fewer insects than still water; and areas infested with ants or bees should be avoided.

A3. There should be an area nearby to construct signals; the entrance should face the sun for warmth and morale; thick woods should be avoided as it will make drying difficult; look for a natural windbreak or place away from strong wind currents; avoid swampy terrain; and choose a place where a fire can be located in front of the opening of the shelter.

Teaching point 2 Explain and Demonstrate the Procedure for Constructing a Lean-to-style Shelter

Time: 20 min Method: Demonstration

While in the field you must adhere to the policies in CATO 11-08, Environmental Protection and Stewardship .

The lean-to-style shelter that was previously constructed is for demonstration purposes and is to be shown to the cadets while providing an explanation of its construction.

The procedure for constructing the lean-to-style shelter are to include:

1. obtaining the appropriate supplies to include:

a. ground sheets,

b. knife,

c. shovel,

d. pegs,

e. rope/twine, and

f. natural materials.

2. tying and lashing cross-pieces and the vertical supports between the trees and ground;

3. checking each ground sheet for fatigue and holes;

4. tying each end of the ground sheet to the cross-pieces and supports, ensuring they are to waist height of the tallest person;

5. substituting the ground sheet for the boughs illustrated in Figure 1;

6. ensuring the ground sheet is pulled tight between the cross-pieces and supports and along the sides;

7. pulling the bottom of the ground sheet out and pegging each grommet to the ground; and

8. digging small trenches around the shelter to allow for effective drainage.

SAFETY

Review safe handling of a knife to include:

• always cut away from the body;

• do not let others stand too close to you;

• do not leave a knife unattended on the ground;

• sheath a knife when not in use; and

• never throw a knife for any reason.

“Shelters”, Wilderness Survival. Copyright 2007 Jalic Inc. Retrieved 9 March 2007, from http://www.wilderness-survival.net/shelters-s.php

Figure 1 Lean-to-style Shelter

CONFIRMATION OF TEACHING POINT 2

QUESTIONS

Q1. What three items are required to build a shelter?

Q2. What is the purpose of digging small trenches around a shelter?

Q3. What is the purpose of the ground sheet and why is it pegged down?

ANTICIPATED ANSWERS

A1. Rope/twine, ground sheets, pegs, branches, sticks and leaves are required.

A2. The small trenches provide drainage.

A3. The ground sheet will keep the occupant dry and the pegs are to secure the ground sheet to the ground.

Teaching point 3 Construct a Lean-to-style Shelter

Time: 40 min Method: Performance

ACTIVITY

OBJECTIVE

The objective of this activity is to have the cadets, in groups of no more than four, construct a lean-to-style shelter.

RESOURCES

• Ground sheets,

• Rope/twine,

• Shovel,

• Items found in a natural setting, and

• Pegs.

ACTIVITY LAYOUT

Select an area that is large enough to construct the lean-to-style shelters.

ACTIVITY INSTRUCTIONS

Working as a member of a group of no more than four, the cadets shall choose a location for the lean-to-style shelter and gather sticks and branches that will be required to build the shelter. Each group shall make sure they have the necessary resources to complete a shelter. Each group shall construct a lean-to-style shelter following these steps:

1. Tie a cross-piece between two trees so that it is to waist height of the tallest person.

2. Lash the support pieces to the cross-piece.

3. Pull the ground sheet tight and tie it to the crosspiece and supports.

4. Pull the bottom of the ground sheet out and peg each grommet to the ground.

5. Dig small trenches for drainage around the lean-to-style shelter.

The questions in the confirmation of TP3 should be asked of the groups as the instructor moves from one group to the next.

SAFETY

Adequate supervision will ensure the cadets do not misuse the equipment.

CONFIRMATION OF TEACHING POINT 3

QUESTIONS

Q1. Why was that location chosen to build the shelter?

Q2. How are the supports anchored?

Q3. What challenges were encountered while building the shelter?

ANTICIPATED ANSWERS

A1. It was built on a flat area, with a little slope; away from animal trails or water holes; away from still water; away from areas infested with ants and bees; having a natural wind break and facing the sun.

A2. They are lashed together between the cross-pieces and the ground.

A3. Answers will vary. Encourage the cadets to elaborate their responses.

END OF LESSON CONFIRMATION

The cadets’ construction of a lean-to-style shelter will serve as the confirmation of this lesson.

CONCLUSION

HOMEWORK/READING/PRACTICE

N/A.

METHOD OF EVALUATION

N/A.

CLOSING STATEMENT

It is important for the cadets to know how to construct a lean-to-style shelter in a survival situation. A shelter will help protect a person from weather, animals and insects. Shelters can also provide warmth, shade and comfort. The lean-to-style shelter provides an effective shelter for squadron survival exercises.

INSTRUCTOR NOTES/REMARKS

If lean-to-style shelters cannot be constructed, another style shelter (e.g. a bivouac tent, or a tarpaulin between trees) may be substituted.

The directives found in CATO 11-08, Environmental Protection and Stewardship , are to be followed during this lesson.

REFERENCES

A0-039 CATO 11-08 D Cdts 3. (1997). Environmental Protection and Stewardship . Vol. 1 General (pp. 1-11). Ottawa, ON: Department of National Defence.

C3-002 (ISBN 0-00-653140-7) Wiseman, J. (1999). The SAS Survival Handbook. Hammersmith, London: HarperCollins Publishers.

C3-003 (ISBN 1-896713-00-9) Tawrell, P. (1996). Camping and Wilderness Survival: The Ultimate Outdoors Book. Green Valley, ON: Falcon Distribution.

C3-118 Wilderness Survival. (2007). Shelters. Retrieved 9 March 2007, from http://www.wilderness-survival.net/shelters-2.php.

Level One · PO 190 – Participate in an aircrew survival exercise 14 EOs

PO 190 – Level One →

Level Three · PO 390 – Navigate a route using a map and compass 19 EOs

PO 390 – Level Three →

Level Four · PO 490 – Participate in an aircrew survival exercise 12 EOs

PO 490 – Level Four →

Level Five · PO 590 – Analyze an aircrew survival case study 1 EO

PO 590 – Level Five →